What Are ASIs in Construction?

Sponsored By

Originally posted by blogadmin on billd .com

In almost every industry, revisions to a project scope, large and small, are inevitable. The construction industry is no different. After signing an agreement for a construction project, there are three ways to alter it:

  • Change orders
  • Construction change directives
  • Architect’s supplemental instructions or ASI

What is ASI in Construction?

An ASI in construction (Architect’s Supplemental Instructions) is a document that contains revisions, changes, and/or additional information that an architect issues to the contractor to supplement the original construction plans, specs and blueprints they provided. ASIs are one of several ways the owner, architect and/or contractor can ask for changes to a project that has already begun. 

Authorized for use by the American Institute of Architects under paragraph 7.4 of A201-1997, an architect can only use an ASI to resolve informational issues or make minor changes that do not affect a construction project’s budget or alter the timeline. ASIs are involved in nearly every kind of construction project— from a family home to a corporate headquarters.

There are two things ASIs in construction absolutely cannot change: 

  • The contract sum
  • The contract time

The use of an ASI would not be an appropriate way to include new specifications that alter the plan in any way. However, although an ASI is reserved for minor changes, they can still affect large portions of the work. 

Billd Commercial Construction Financing

5e34ac91fe8a100001b3e1d0Loading TrustPilot
Billd is a payment solution that allows construction contractors to offer 120-day terms to pay for materials and suppliers to sell more.

Examples of an ASI include:

  • Trim configurations (at complex intersections)
  • Lighting or electrical layouts (how an exterior light actually connects to the siding material)
  • Transitions between materials that had not been previously thought out

Reasons for an ASIs include:

  • Changes in material/equipment/fixture selection
  • Details that had not been previously determined in the construction plan set
  • Recognition of error/omission
  • In response to an RFI
  • Reviewing agency request
  • Request by the project owner
  • Changed conditions
  • Request for substitution

What Subcontractors Should Do When They Receive an ASI

Once a subcontractor is alerted to an ASI, the clock starts ticking. The first thing they need to do is verify that work has not yet begun before moving forward. 

Pro Tip: If work has already begun, the ASI must be rescinded, and a change order needs to be issued to add in the new cost and additional time to the contract. While the ASI stipulates there is to be no change to the cost or the time, this is where subcontractors need to be mindful. If the subcontractor begins to enact these changes, they have given up their right to ask for further compensation or time.

After moving forward on an ASI in construction, (assuming it won’t actually affect the cost or time on a project), it is imperative that it be added to the contract documents once it’s been created. The general contractor must ensure that the subcontractor receives the ASI immediately. The GC will also need to include the change on any further documentation, including applications for payment.

How ASIs Can Affect a Sub’s Pay App

Although ASIs may only deal with small changes, you should tread carefully with them. If they’re mishandled or misunderstood, it can be costly for a sub. Even though the contract sum won’t change on account of an ASI, this does not mean that an ASI can’t affect your application for payment. If the pay app doesn’t reflect the change made in the ASI, payment will probably stall. This is why a subcontractor must ensure that an ASI is included in the contract documents (and confirm that it won’t affect cost or time).

Billd Commercial Construction Financing

5e34ac91fe8a100001b3e1d0Loading TrustPilot
Billd is a payment solution that allows construction contractors to offer 120-day terms to pay for materials and suppliers to sell more.

The Difference Between ASIs and CCDs

Both ASIs and CCDs are tools to revise the scope of a construction project, but construction change directives differ from ASIs pretty substantially. Unlike a change order, which requires an agreement between the project owner and the contractor, a CCD is used when no agreement can be reached. As a result, the architect makes the final decision. CCDs are not requests, they are essentially forced directions that a contractor will have to figure out how to handle. Both ASIs and CCDs hinge on the architect’s involvement and judgment.  

The contractor can either agree to the changes in price or timing or dispute the agreement. And while a CCD can be helpful to the owner, due to its often contentious nature, it is no surprise that some of these disagreements lead to litigation. Still, the contractor is expected to perform the work specified while the dispute is pending.

Construction project changes are inevitable. Without a well-written contract to guide the execution of these changes, disputes can arise. The first step to avoid disputes is to get acquainted with the ins and outs of construction contract terms like ASIs. 

Billd.com

The post What Are ASIs in Construction? appeared first on Billd.

You may also like

Being a general contractor or subcontractor, lucrative contracts are the lifeblood of your business. Here’s how to craft winning proposals.
Read more

Advertisement Disclosure

Product name, logo, brands, and other trademarks featured or referred to within Banks.com are the property of their respective trademark holders. This site may be compensated through third party advertisers. The offers that may appear on Banks.com’s website are from companies from which Banks.com may receive compensation. This compensation may influence the selection, appearance, and order of appearance of the offers listed on the website. However, this compensation also facilitates the provision by Banks.com of certain services to you at no charge. The website does not include all financial services companies or all of their available product and service offerings.